Start time
|
Planned duration
|
Item description
|
Speaker
|
1st day: 9th July 2018
|
9:30
|
15 min
|
Welcome
|
CERTH
|
9:45
|
45 min
|
WP8: Project management and impact creation
|
UPM
|
10:30
|
75 min
|
WP1: Requirements, specification and technical architecture
-
T1.2: EasyTV system requirement specification: planning, overview of the work to be done/done, deliverables and milestones.
-
T1.3: Technical architecture development: overview of work done; problems encountered and proposed solutions; plans for the second version.
|
ENG
|
11:45
|
15 min
|
Coffee break
|
|
12:00
|
90 min
|
WP2: improved access services for improve multimedia viewing, hearing and description
-
T2.1, T2.2, T2.4: planning, overview of the work to be done/done, deliverables and milestones
-
T2.3: presentation and planning
NOTE: from 12:30 to 13:00: demos of the developments (to be defined)
|
UPM
|
13:30
|
60 min
|
Lunch
|
|
14:30
|
90 min
|
WP3: Novel technologies for interaction with content and users and break the language barrier…
-
T3.1, T3.2, T3.4: planning, overview of the work to be done/done, deliverables and milestones
-
T3.3 and T3.5: presentation and planning
NOTE: from 15:00 to 15:30: demos of the developments (to be defined)
|
MV
|
16:00
|
90 min
|
WP4: Improved personalization
-
T4.1, T4.2, T4.3: planning, overview of the work to be done/done, deliverables and milestones
NOTE: from 16:30 to 17:00: demos of the developments (to be defined)
|
CERTH
|
2nd day: 10th July 2018
|
9:15
|
75 min
|
WP5: EasyTV component based system
-
T5.1, T5.2, T5.3, T5.4: planning, overview of the work to be done/done, deliverables and milestones
-
T5.5: planning, overview of the work to be done, deliverables and milestones
|
ENG
|
10:30
|
30 min
|
Coffee break
|
|
11:00
|
60 min
|
WP6: Testing with users and feedback to the platform
-
T6.1: planning, overview of the work to be done/done, deliverables and milestones
-
T6.2: planning, overview of the work to be done, deliverables and milestones
|
UAB
|
12:00
|
60 min
|
WP7: Dissemination and exploitation:
Open issues: normal dissemination of the project: press, web page, material, etc.
|
ENG
|
13:00
|
30 min
|
Time for additional discussion and review of actions
|
ALL
|
13:30
|
30 min
|
Recap and next steps
|
UPM
|